01Cost Variance & Schedule Variance
Three numbers drive everything: PV, EV, AC.
PV โ Planned Value
Budgeted cost of work planned by now.EV โ Earned Value
Budgeted cost of work actually done.AC โ Actual Cost
What the done work really cost.Negative = bad. CV<0 over budget ยท SV<0 behind schedule.
Week 1 example (PKR M)
SV = 32 โ 40 = โ8 behind schedule. AC alone (38 vs 40) wrongly looks โon trackโ โ EVM catches it.
02CPI, SPI & EAC
Ratios instead of differences. Above 1.0 = better than plan.
๐งฎ Try it โ live EVM calculator
Default = Gulberg Commercial Block, Month 6. Drag the sliders.
*TCPI = (BAC โ EV) / (BAC โ AC): CPI needed from now to finish on budget (bonus question).
Worked answer โ Month 6 health check (PKR M)
| Measure | Working | Result | Meaning |
|---|---|---|---|
| CV | 100 โ 115 | โ15 | Over budget |
| SV | 100 โ 120 | โ20 | Behind schedule |
| CPI | 100 / 115 | 0.87 | 87 paisa of work per 1 rupee |
| SPI | 100 / 120 | 0.83 | 83% of planned work done |
| EAC | 240 / 0.87 | โ 276 | PKR 36M over the 240 budget |
| TCPI | (240โ100)/(240โ115) | 1.12 | Must be 12% more efficient to finish at 240 |
03Reading EVM Results
One glance tells you the projectโs health.
| Cost (CV / CPI) | Schedule (SV / SPI) | |
|---|---|---|
| Positive / > 1 | Under budget | Ahead |
| Zero / = 1 | On budget | On schedule |
| Negative / < 1 | Over budget | Behind |
Month 6 S-curve (PKR M)
EV below PV โ 20M of work late. AC above EV โ 15M extra cost. Gap widens monthly.
04Definition of Cost Control
๐ Continuous
Repeated weekly/monthly โ not an end-of-project event.๐ When
Mostly Phase 4 (Construction), but depends on baseline quality from Phases 1โ3.โ Why overruns happen
Many small manageable variances โ not one big error.Cost influence vs cost of change
๐ Estimation
Bad initial estimate, incomplete scope, low contingency๐ Market
Steel/cement prices, rupee fall, shortages๐งญ Management
Poor monitoring, slow decisions, weak change control๐ External
LDA approval delays, mid-build design changesโ The four overrun categories (Raiwind Road case: steel +22% = market, 3 layout changes = management, LDA 6 weeks = external).
05The Cost Control Cycle
Plan โ Measure โ Compare โ Act โ repeat.
Week 4 expanded loop (5 steps)
Tools: cost codes (WBS), cost ledger, committed cost log, variance report, forecast to complete.
06Estimate vs Budget
Estimate = what work should cost (forecast). Budget = money the organisation authorises (baseline).
| Estimating | Budgeting | Cost Control | |
|---|---|---|---|
| When | Pre-contract / design | At award / baseline | During construction |
| Purpose | Predict likely cost | Allocate approved funds over time | Track & correct spend |
| Output | Figure / range | Time-phased baseline (S-curve) | Variance reports, forecasts |
| Owner | Estimator / QS | PM / Client | Cost Control Manager |
Estimate ยท Budget ยท Bid ยท Price
| Term | By | Meaning |
|---|---|---|
| Estimate | Consultant / contractor | Forecast of cost |
| Budget | Owner / PM | Approved money = baseline |
| Bid | Contractor | Offer to build for a sum |
| Price | Both | Agreed contract sum |
Estimate โ Budget (Gulberg, PKR 240M)
Estimate classes (AACE) โ accuracy improves as design matures
| Class | Design done | Purpose | Typical method | Range |
|---|---|---|---|---|
| 5 | 0โ2% | Concept screening | Order of magnitude | โ35% / +65% |
| 4 | 1โ15% | Feasibility | Area based / parametric | โ23% / +35% |
| 3 | 10โ40% | Budget authorisation | Elemental (UniFormat) | โ15% / +20% |
| 2 | 30โ75% | Control or bid | Quantity take-off | โ10% / +13% |
| 1 | 65โ100% | Check estimate / bid | Priced BOQ | โ7% / +9% |
07Area-Based Estimate with Location Factor
| Input | Value |
|---|---|
| Covered area | 30,000 sq ft |
| Base rate | PKR 8,000 / sq ft |
| Location factor (access, ground) | ร 1.05 |
| Time adjustment | ร 1.10 |
| Estimate | PKR 277.2 M |
Build-up
Class 4 โ real cost could land โ PKR 194M โ 416M.
08Cost Index Method (Parametric)
Cost index โ move old cost to today
180 ร (195 / 150) = 180 ร 1.30 = PKR 234 M
Q2: 150 ร (180 / 120) = PKR 225 M
Capacity factor โ six-tenths rule
2,000 mยณ reservoir = 40M
5,000 mยณ โ 40 ร 2.5^0.6 = 40 ร 1.73 = PKR 69.3 M
2.5ร size but only 1.73ร cost โ economies of scale.
Four estimating techniques compared
| Technique | Basis | Needs | Stage | Class |
|---|---|---|---|---|
| Area / unit | Cost per mยฒ from similar projects | Area, building type | Feasibility, concept | 5โ4 |
| Parametric / index | Capacity & time relationships | One past project | Concept | 5โ4 |
| Elemental | Cost per element (UniFormat AโG) | Element areas, outline spec | Schematic | 3 |
| Detailed take-off | Qty ร unit rate (MasterFormat, BOQ) | Full drawings & spec | Tender | 2โ1 |
09Contingency & Escalation
๐ก Contingency
- Covers unknowns inside defined scope
- Shrinks as design matures
- Held & managed โ not padding in every rate
- Scope changes = change orders, not contingency
๐ Escalation (inflation over time)
i = annual rate, n = years to construction mid-point. At 6%:
From direct cost to tender price โ order matters (each % on running total)
| Step | Basis | PKR M | Running |
|---|---|---|---|
| Direct cost | Qty ร unit rates | 100.00 | 100.00 |
| Preliminaries | 8% | 8.00 | 108.00 |
| Head office OH | 5% | 5.40 | 113.40 |
| Contingency | 5% | 5.67 | 119.07 |
| Profit | 8% | 9.53 | 128.60 |
| Escalation | 3% (6%/yr ร ยฝ yr) | 3.86 | 132.46 |
| Tender price | โ +32% markups | 32.46 | 132.46 |
Unit rate โ 1 mยณ concrete
| Materials | 16,000 |
| Waste 5% | 800 |
| Labour 4 ร 1,500 | 6,000 |
| Equipment | 1,200 |
| Direct cost | 24,000 |
| Site OH 10% | 2,400 |
| Profit 10% of 26,400 | 2,640 |
| Unit rate | 29,040 / mยณ |
22.44 mยณ ร 29,040 = PKR 651,658 ยท Q3: 12,000 ร 1.1 ร 1.1 = 14,520
10Cash Flow Gap, Payment Delay & Retention
Spend follows the work, cash comes later โ contractor funds the gap.
Fixes: faster payment (15 days) ยท mobilisation advance (10% = 24M) ยท cut retention to 5%. Delaying subcontractor payments = risky/unethical.
Key idea: profitable projects can still run out of cash.
11Variance Report
Negative / (brackets) = over budget. Investigate anything beyond ยฑ5%.
| Code | Item | Budget | Actual | Variance | % | Flag |
|---|---|---|---|---|---|---|
| 03-100 | Concrete | 22.0 | 24.6 | (2.6) | (11.8%) | Investigate โ overspend |
| 05-100 | Steel | 14.0 | 14.4 | (0.4) | (2.9%) | OK |
| 09-200 | Blockwork & plaster | 9.0 | 8.1 | 0.9 | 10.0% | Investigate โ underspend |
| 01-300 | Site overheads | 6.0 | 6.2 | (0.2) | (3.3%) | OK |
| Total | 51.0 | 53.3 | (2.3) | (4.5%) |
12Also on the Midterm (Weeks 1โ7)
Project cost lifecycle
Key roles
| Client | Approves budget & contingency |
| PM | Owns cost performance |
| QS | BOQs, measures, payment certificates |
| Cost Control Eng. | Runs EVM / variance |
| Site Manager | Reports progress, flags risk |
Change orders (Week 7)
Request โ Price & time โ Approve โ Update budget โ Track
| Type | Usually pays |
|---|---|
| Owner directed | Client |
| Design error | Designer / client |
| Unforeseen condition | Shared (contract) |
| Contractor initiated | Contractor |
Faรงade: (9,500 โ 2,500) ร 3,200 = 22.4M ร 1.1 = 24.64M, +6 weeks
Control systems tiers
| T1 | Excel / manual BOQ | Small firms |
| T2 | MS Project, Primavera P6 | Mid-size |
| T3 | SAP, Unifier, 5D BIM | Large |
Common estimating errors
Missing scope ยท double counting ยท stale rates ยท unit mix-ups ยท ignored site conditions ยท no range stated.
Good cost report answers 4 questions
- Where are we?
- Why are we here?
- Where will we end?
- What do we need from the Board?
Detailed estimate โ 6 steps
- Study documents
- Take off quantities
- Price resources
- Build unit rates
- Add markups
- Review & issue
13One-Page Formula Cheat Sheet
| Formula | Expression | Good when |
|---|---|---|
| CV | EV โ AC | > 0 |
| SV | EV โ PV | > 0 |
| CPI | EV / AC | > 1 |
| SPI | EV / PV | > 1 |
| EAC | BAC / CPI | โค BAC |
| TCPI | (BAC โ EV) / (BAC โ AC) | โค 1 |
| Variance | Budget โ Actual | โฅ 0 |
| Variance % | Variance / Budget ร 100 | within ยฑ5% |
| Area estimate | Area ร Rate ร Loc ร Time | โ |
| Cost index | Past ร (Index now / then) | โ |
| Capacity | Cโ ร (Sโ/Sโ)^0.6 | โ |
| Escalation | Base ร (1 + i)โฟ | โ |
| Estimate | Quantity ร Rate + Markups | โ |
14Practice Cards