CMT-422 Midterm Prep

Cost Control & Value Engineering โ€” short answers, animated graphs, tables and worked numbers for every midterm topic.

๐Ÿ“˜ Weeks 1โ€“7โฑ 20 min revision๐Ÿงฎ All formulas๐Ÿƒ Practice cards

01Cost Variance & Schedule Variance

Three numbers drive everything: PV, EV, AC.

PV โ€” Planned Value

Budgeted cost of work planned by now.

EV โ€” Earned Value

Budgeted cost of work actually done.

AC โ€” Actual Cost

What the done work really cost.
CV = EV โˆ’ AC
โ†’ cost
SV = EV โˆ’ PV
โ†’ schedule

Negative = bad. CV<0 over budget ยท SV<0 behind schedule.

Memory trick: EV always comes first. Cost โ†’ compare with AC. Schedule โ†’ compare with PV.

Week 1 example (PKR M)

PV40 EV32 AC38 CV = 32 โˆ’ 38 = โˆ’6 over budget

SV = 32 โˆ’ 40 = โˆ’8 behind schedule. AC alone (38 vs 40) wrongly looks โ€œon trackโ€ โ€” EVM catches it.

02CPI, SPI & EAC

Ratios instead of differences. Above 1.0 = better than plan.

CPI = EV / AC
Value earned per 1 rupee spent
SPI = EV / PV
Work done vs work planned
EAC = BAC / CPI
Forecast final cost (BAC = total budget)

๐Ÿงฎ Try it โ€” live EVM calculator

Default = Gulberg Commercial Block, Month 6. Drag the sliders.

CV
SV
CPI
SPI
EAC
TCPI*

*TCPI = (BAC โˆ’ EV) / (BAC โˆ’ AC): CPI needed from now to finish on budget (bonus question).

Worked answer โ€” Month 6 health check (PKR M)

MeasureWorkingResultMeaning
CV100 โˆ’ 115โˆ’15Over budget
SV100 โˆ’ 120โˆ’20Behind schedule
CPI100 / 1150.8787 paisa of work per 1 rupee
SPI100 / 1200.8383% of planned work done
EAC240 / 0.87โ‰ˆ 276PKR 36M over the 240 budget
TCPI(240โˆ’100)/(240โˆ’115)1.12Must be 12% more efficient to finish at 240
Poll answer: โ€œSpent 115 vs planned 120 = 5M under budgetโ€ is a trap. Answer is B โ€” In trouble.

03Reading EVM Results

One glance tells you the projectโ€™s health.

Cost (CV / CPI)Schedule (SV / SPI)
Positive / > 1Under budgetAhead
Zero / = 1On budgetOn schedule
Negative / < 1Over budgetBehind
EAC > BAC โ†’ project will finish over budget.

Month 6 S-curve (PKR M)

PV planEV earnedAC actual

EV below PV โ†’ 20M of work late. AC above EV โ†’ 15M extra cost. Gap widens monthly.

04Definition of Cost Control

Cost control = the ongoing process of monitoring actual spend against the approved budget (baseline), spotting variances early, and taking corrective action to keep the project within financial limits.

๐Ÿ” Continuous

Repeated weekly/monthly โ€” not an end-of-project event.

๐Ÿ— When

Mostly Phase 4 (Construction), but depends on baseline quality from Phases 1โ€“3.

โš  Why overruns happen

Many small manageable variances โ€” not one big error.

Cost influence vs cost of change

Ability to influence final costCost of making a change
Exam point: change early = cheap. By construction, most of the cheap opportunity is gone.

๐Ÿ“ Estimation

Bad initial estimate, incomplete scope, low contingency

๐Ÿ“ˆ Market

Steel/cement prices, rupee fall, shortages

๐Ÿงญ Management

Poor monitoring, slow decisions, weak change control

๐Ÿ› External

LDA approval delays, mid-build design changes

โ†‘ The four overrun categories (Raiwind Road case: steel +22% = market, 3 layout changes = management, LDA 6 weeks = external).

05The Cost Control Cycle

Plan โ†’ Measure โ†’ Compare โ†’ Act โ†’ repeat.

1 PLANbaseline 2 MEASUREactual spend 3 COMPAREvariance 4 ACTcorrect weekly / monthly

Week 4 expanded loop (5 steps)

1 BaselineBudget by cost code & month
2 MeasureActual + committed cost
3 CompareVariance vs baseline
4 AnalyseFind the cause, not the symptom
5 ActCorrect, then re-forecast

Tools: cost codes (WBS), cost ledger, committed cost log, variance report, forecast to complete.

06Estimate vs Budget

Estimate = what work should cost (forecast). Budget = money the organisation authorises (baseline).

EstimatingBudgetingCost Control
WhenPre-contract / designAt award / baselineDuring construction
PurposePredict likely costAllocate approved funds over timeTrack & correct spend
OutputFigure / rangeTime-phased baseline (S-curve)Variance reports, forecasts
OwnerEstimator / QSPM / ClientCost Control Manager

Estimate ยท Budget ยท Bid ยท Price

TermByMeaning
EstimateConsultant / contractorForecast of cost
BudgetOwner / PMApproved money = baseline
BidContractorOffer to build for a sum
PriceBothAgreed contract sum

Estimate โ†’ Budget (Gulberg, PKR 240M)

Estimate classes (AACE) โ€” accuracy improves as design matures

ClassDesign donePurposeTypical methodRange
50โ€“2%Concept screeningOrder of magnitudeโˆ’35% / +65%
41โ€“15%FeasibilityArea based / parametricโˆ’23% / +35%
310โ€“40%Budget authorisationElemental (UniFormat)โˆ’15% / +20%
230โ€“75%Control or bidQuantity take-offโˆ’10% / +13%
165โ€“100%Check estimate / bidPriced BOQโˆ’7% / +9%
Rule: always quote the class and range with the number. Accuracy comes from design definition, not decimals.

07Area-Based Estimate with Location Factor

Estimate = Area ร— Rate ร— Location factor ร— Time factor
InputValue
Covered area30,000 sq ft
Base ratePKR 8,000 / sq ft
Location factor (access, ground)ร— 1.05
Time adjustmentร— 1.10
EstimatePKR 277.2 M

Build-up

240 252 277.2 Areaร—Rateร—1.05 locร—1.10 time

Class 4 โ†’ real cost could land โ‰ˆ PKR 194M โ€“ 416M.

Cafรฉ exercise: 2,400 ร— 7,000 = 16.8M โ†’ +10% contingency = 18.48M โ†’ +3% escalation = โ‰ˆ PKR 19.03M, quote as Class 4โ€“5 with a range.

08Cost Index Method (Parametric)

Cost index โ€” move old cost to today

Cost now = Past cost ร— (Index now / Index then)

180 ร— (195 / 150) = 180 ร— 1.30 = PKR 234 M

Q2: 150 ร— (180 / 120) = PKR 225 M

Capacity factor โ€” six-tenths rule

Cโ‚‚ = Cโ‚ ร— (Sโ‚‚ / Sโ‚)โฟ   n โ‰ˆ 0.6

2,000 mยณ reservoir = 40M
5,000 mยณ โ†’ 40 ร— 2.5^0.6 = 40 ร— 1.73 = PKR 69.3 M

2.5ร— size but only 1.73ร— cost โ†’ economies of scale.

Four estimating techniques compared

TechniqueBasisNeedsStageClass
Area / unitCost per mยฒ from similar projectsArea, building typeFeasibility, concept5โ€“4
Parametric / indexCapacity & time relationshipsOne past projectConcept5โ€“4
ElementalCost per element (UniFormat Aโ€“G)Element areas, outline specSchematic3
Detailed take-offQty ร— unit rate (MasterFormat, BOQ)Full drawings & specTender2โ€“1
UniFormat = by building element (A Substructure โ†’ G Sitework), for design decisions. MasterFormat = by trade (03 Concrete, 09 Finishes), for BOQ & buying.

09Contingency & Escalation

๐Ÿ›ก Contingency

  • Covers unknowns inside defined scope
  • Shrinks as design matures
  • Held & managed โ€” not padding in every rate
  • Scope changes = change orders, not contingency
One-liner: contingency covers unknowns, escalation covers time.

๐Ÿ“ˆ Escalation (inflation over time)

Future = Base ร— (1 + i)โฟ

i = annual rate, n = years to construction mid-point. At 6%:

From direct cost to tender price โ€” order matters (each % on running total)

StepBasisPKR MRunning
Direct costQty ร— unit rates100.00100.00
Preliminaries8%8.00108.00
Head office OH5%5.40113.40
Contingency5%5.67119.07
Profit8%9.53128.60
Escalation3% (6%/yr ร— ยฝ yr)3.86132.46
Tender priceโ‰ˆ +32% markups32.46132.46

Unit rate โ€” 1 mยณ concrete

Materials16,000
Waste 5%800
Labour 4 ร— 1,5006,000
Equipment1,200
Direct cost24,000
Site OH 10%2,400
Profit 10% of 26,4002,640
Unit rate29,040 / mยณ

22.44 mยณ ร— 29,040 = PKR 651,658 ยท Q3: 12,000 ร— 1.1 ร— 1.1 = 14,520

10Cash Flow Gap, Payment Delay & Retention

Spend follows the work, cash comes later โ†’ contractor funds the gap.

Cumulative cash outCumulative cash inGap
30.5M
Peak gap ยท Month 4
30 days
Payment delay after certification
10%
Retention held back
20M
Credit line (short by 10.5M)
Gap = cash out โˆ’ cash in. Payment delay shifts cash-in right. Retention lowers each payment. Both widen the gap.

Fixes: faster payment (15 days) ยท mobilisation advance (10% = 24M) ยท cut retention to 5%. Delaying subcontractor payments = risky/unethical.

Key idea: profitable projects can still run out of cash.

11Variance Report

Variance = Budget โˆ’ Actual
 
Variance % = Variance / Budget ร— 100

Negative / (brackets) = over budget. Investigate anything beyond ยฑ5%.

CodeItemBudgetActualVariance%Flag
03-100Concrete22.024.6(2.6)(11.8%)Investigate โ€” overspend
05-100Steel14.014.4(0.4)(2.9%)OK
09-200Blockwork & plaster9.08.10.910.0%Investigate โ€” underspend
01-300Site overheads6.06.2(0.2)(3.3%)OK
Total51.053.3(2.3)(4.5%)
Underspend isnโ€™t always good โ€” it may mean work is late or costs not yet booked.

12Also on the Midterm (Weeks 1โ€“7)

Project cost lifecycle

FeasibilityRough est.
โ†’
DesignDetailed, VE
โ†’
TenderBaseline
โ†’
ConstructionEVM, variance
โ†’
Close-outFinal account

Key roles

ClientApproves budget & contingency
PMOwns cost performance
QSBOQs, measures, payment certificates
Cost Control Eng.Runs EVM / variance
Site ManagerReports progress, flags risk

Change orders (Week 7)

Request โ†’ Price & time โ†’ Approve โ†’ Update budget โ†’ Track

TypeUsually pays
Owner directedClient
Design errorDesigner / client
Unforeseen conditionShared (contract)
Contractor initiatedContractor

Faรงade: (9,500 โˆ’ 2,500) ร— 3,200 = 22.4M ร— 1.1 = 24.64M, +6 weeks

Control systems tiers

T1Excel / manual BOQSmall firms
T2MS Project, Primavera P6Mid-size
T3SAP, Unifier, 5D BIMLarge

Common estimating errors

Missing scope ยท double counting ยท stale rates ยท unit mix-ups ยท ignored site conditions ยท no range stated.

Good cost report answers 4 questions

  1. Where are we?
  2. Why are we here?
  3. Where will we end?
  4. What do we need from the Board?

Detailed estimate โ€” 6 steps

  1. Study documents
  2. Take off quantities
  3. Price resources
  4. Build unit rates
  5. Add markups
  6. Review & issue

13One-Page Formula Cheat Sheet

FormulaExpressionGood when
CVEV โˆ’ AC> 0
SVEV โˆ’ PV> 0
CPIEV / AC> 1
SPIEV / PV> 1
EACBAC / CPIโ‰ค BAC
TCPI(BAC โˆ’ EV) / (BAC โˆ’ AC)โ‰ค 1
VarianceBudget โˆ’ Actualโ‰ฅ 0
Variance %Variance / Budget ร— 100within ยฑ5%
Area estimateArea ร— Rate ร— Loc ร— Timeโ€”
Cost indexPast ร— (Index now / then)โ€”
CapacityCโ‚ ร— (Sโ‚‚/Sโ‚)^0.6โ€”
EscalationBase ร— (1 + i)โฟโ€”
EstimateQuantity ร— Rate + Markupsโ€”